The most gratifying after service
A good exam dump like Construction-Manager exam simulator should own considerate service. Just high quality is far from excellent. Contrasting with many other exam dumps, the Construction-Manager exam dump has unsurpassable quality as well as the unreachable heights service. In some other exam dumps, you may be neglected at the time you buy their products. It's impossible that you have nothing to do with us after buying CMAA Construction-Manager pass-sure dumps. We cannot ignore any problem you meet after choose Construction-Manager exam dump, you are welcomed to ask our service system any time if you come across any doubt. As the exam dump leader, the Construction-Manager exam simulator will bring you the highest level service rather than just good. That is why purchasing Construction-Manager pass-sure dumps have become a kind of pleasure rather than just consumption.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
There are three main reasons that you will purchase a product. First you need it. Second, the product has high quality. Third, the throughout service is accompanied with the product. Now here the Construction-Manager pass-sure dumps in front of you with far more than these three reasons. You can't miss it.
Unbelievable convenient
As we mentioned just now, what Construction-Manager exam dump are not only the highest level quality and service but also something more. For instance, it provides you the most convenient delivery way to you. Nobody prefers complex and troubles. As the best exam dump, Construction-Manager pass-sure dumps must own high standard equipment in all aspects. The aspect even is extended to the delivery way. Many candidates may give up the goods result from the complex and long time delivery. However, it can't exist on the way of Construction-Manager exam simulator. We have a card up our sleeves that all materials of CMAA Construction-Manager exam dump will in your hand with ten minutes for that Construction-Manager pass-sure dumps supports the e-mail manner to delivery fields which guarantees the absolutely convenient delivery way for you.
Remarkable quality of CMAA Construction-Manager exam dump
First of all, of course you need Construction-Manager exam dump if you want pass the exam and take an advantage position in the fierce competition world. Then what's more important, the absolutely high quality of CMAA Construction-Manager exam simulator is the fundamental reason for us to introduce it to all of you with fully confidence. You must have known high quality means what. It can be amount to high pass rate. That's to say the Construction-Manager pass-sure dumps which owns the highest quality owns the highest pass rate. Of course, we do not take this for granted. We do feedbacks and relative researches regularly, as we thought, totally all have passed the examination who choose Construction-Manager exam simulator. Okay, now aside this significant research. As the back power of Construction-Manager exam dump also can totally support such high quality. The best and strongest teams---from the study team to the after service are all stand behind the exam dump. Once you choose Construction-Manager pass-sure dumps means such strong power same standing behind you. In other words, it just like that you are standing on the shoulder of giants when you are with the Construction-Manager exam simulator.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Safety Management | 10% | - Regulatory compliance - Safety planning and training - Incident investigation - Hazard identification and control |
| Topic 2: Technology | 5% | - BIM and digital tools - Emerging technologies - Project management software - Data management and analytics |
| Topic 3: Program & Project Management | 20% | - Scope management - Stakeholder management - Lifecycle management - Project initiation and planning |
| Topic 4: Sustainability | 5% | - Environmental compliance - Lifecycle assessment - Green building principles - Resource efficiency |
| Topic 5: Contract Administration | 10% | - Claims and dispute resolution - Contract types and procurement - Negotiation and formation - Change order management |
| Topic 6: Risk Management | 10% | - Insurance and liability - Mitigation and response planning - Identification and assessment - Monitoring and control |
| Topic 7: Quality Management | 10% | - Continuous improvement - Compliance and audits - Quality assurance and control - Planning and standards |
| Topic 8: Time Management | 10% | - Critical path method - Scheduling techniques - Schedule control - Resource allocation and leveling |
| Topic 9: Professional Practice | 10% | - Ethics and standards - Legal and regulatory framework - Professional development - Leadership and communication |
| Topic 10: Cost Management | 10% | - Financial reporting - Earned value management - Estimation and budgeting - Cost control and forecasting |
CMAA Certified Construction Manager (CCM) Sample Questions:
1. The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
A) CxA
B) Regulatory agencies
C) Designer
D) CM
2. A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am-7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should
A) tell the contractor they have until September 1 and can only work 7am-7pm.
B) meet with the owner and contractor to vet all issues/options and make a decision.
C) meet with the contractor to go over realistic time frames and make a decision.
D) discuss with the owner and tell the contractor to do only 1/2 of the bridge.
3. Which of the following provides details about the front-end activities of the project during the pre-design and design phases, and highlights major project milestones such as substantial and final completion?
A) Master Schedule
B) Milestone Schedule
C) Baseline Schedule
D) As-Built Schedule
4. Which of the following contract types limits the potential incentive to increase profit through increasing contract costs?
A) Cost plus a percentage of cost
B) Cost plus fixed fee
C) Unit price
D) Time and materials
5. An agency CM is representing the public owner of a large, complex project with numerous site challenges.
The owner has received numerous differing site condition claims on previous projects on this site. The agency CM has reviewed the bid documents and believes the site challenges are clearly and sufficiently detailed for bidders. This is a design-bid-build, lump sum procurement. The apparent low bid is more than 10% lower than the next lowest bid, and the owner is very concerned that the apparent low bidder has not included the cost of mitigating the site challenges in its bid. What should the agency CM do?
A) Ask the designer to verify that the technical specifications describing the site challenges in sufficient detail.
B) Make the recommendation to the owner to reject all bids and re-advertise the project.
C) Conduct a post-bid interview with the apparent low bidder to determine if the bidder has a clear understanding of the site challenges.
D) Conduct a post-bid conference to see if all bidders included the cost of mitigating the site challenges in their bids.
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: B | Question # 3 Answer: B | Question # 4 Answer: B | Question # 5 Answer: A |