NEW QUESTION 52
SAP Activate uses concepts, ceremonies, roles introduced by SCRUM methodology and expands them with Solution Implementation specifics.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 53
In which tools can the project team across the SAP Activate Methodology content including accelerators? There are 2 answers to this question.

  • A. SAP Jam
  • B. Roadmap Viewer
  • C. SAP Community Network
  • D. SAP Service Marketplace

Answer: A,B

 

NEW QUESTION 54
What does SAP Activate recommend to keep team members informed and aligned?

  • A. Daily team stand-up meeting
  • B. Daily e-mail status updates to project manager
  • C. Daily progress review meeting with sponsor
  • D. Daily status meeting with project manager

Answer: A

 

NEW QUESTION 55
What is a strategy level 0 (L0) artifact?

  • A. Approach document that is developed by a united project team (partner + customer)
  • B. Optional information that is NOT important for project activities
  • C. Preliminary strategy developed by the customer to approach the project in a specific area
  • D. Project result that is developed solely by the partner

Answer: C

 

NEW QUESTION 56
What is the most granular level of the methodology you can view in the SAP roadmap viewer?

  • A. Deliverables
  • B. Task
  • C. Scenario
  • D. Phase

Answer: B

 

NEW QUESTION 57
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape?
There are 2 answers to this question.

  • A. P-system
  • B. DEV
  • C. Starter system
  • D. QAS

Answer: B,D

 

NEW QUESTION 58
Which of the following are benefits of using ready-to-use content? Note: There are 2 correct Answers to this question.

  • A. Exhaustive solution documentation
  • B. Predictable results
  • C. Minimized total cost of ownership
  • D. Fast time-to-value

Answer: B,D

 

NEW QUESTION 59
In which phase do you create "an ordered list of everything that is known to be needed in the Product?

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: D

 

NEW QUESTION 60
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?

  • A. Validation Workshops
  • B. Data Migration Approach
  • C. Design for the Gaps and Deltas
  • D. Baseline Build
  • E. Solution Scope and Value Determination

Answer: A,B,C

 

NEW QUESTION 61
Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?

  • A. Simplification and custom code impact analysis
  • B. Solution validation and Delta design
  • C. Fit-to-standard
  • D. Setup and enablement

Answer: C

 

NEW QUESTION 62
What are some of the benefits that apply to SAP Cloud ALM as a cloud product? Note: There are 2 answers to this question.

  • A. The solution is always available.
  • B. User management is provided.
  • C. The solution is always up to date.
  • D. Different customer landscapes are all managed by SAP.

Answer: A,C

 

NEW QUESTION 63
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the answer.

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: C

 

NEW QUESTION 64
What are some of the capabilities end users can utilize to adapt and change their launchpad home page according to the way they work?

  • A. Rearrange or move tiles within a group
  • B. Delete a predelivered group
  • C. Add any SAP Fiori apps to a group, regardless of role
  • D. Add a new group
  • E. Rename a predelivered tile

Answer: A,D,E

 

NEW QUESTION 65
What are the three elements of SAP Activate? There are 3 correct answers to this question.

  • A. Focused Build Content
  • B. Methodology
  • C. Content
  • D. Tools
  • E. SAP Solution Manager

Answer: B,C,D

 

NEW QUESTION 66
What activities do you perform during the fit-to-standard workshops milestone in the SAP Activate methodology within SAP Cloud ALM? Note: There are 3 correct Answers to this question.

  • A. Create notes and/or requirements in SAP Cloud ALM.
  • B. Create wireframes for user interfaces in SAP Cloud ALM.
  • C. View details of business process diagrams and descriptions in SAP Cloud ALM.
  • D. Create SAP Fiori screen mock-ups in SAP Cloud ALM.
  • E. View details of high-level process flows in SAP Cloud ALM.

Answer: A,C,E

 

NEW QUESTION 67
Which of the following types of monitoring are part of SAP Cloud ALM for operations? Note: There are 2 answers to this question.

  • A. Event and alert monitoring
  • B. Business process monitoring
  • C. Business user monitoring
  • D. Integration and exception monitoring

Answer: B,D

 

NEW QUESTION 68
Which core capability of SAP Cloud ALM for implementation supports the management of the requirements lifecycle?

  • A. Task Management
  • B. Process Management
  • C. Change and Deployment Management
  • D. Test Management

Answer: C

 

NEW QUESTION 69
Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 answers to this question.

  • A. Reporting functional specifications
  • B. Functional specifications
  • C. Functional test scenarios
  • D. User acceptance test-plan

Answer: C,D

 

NEW QUESTION 70
What do you do during post cutover?

  • A. Perform the Verification Session of the SAP Going Live Check
  • B. Setup Operational Support
  • C. Perform Technical System Test
  • D. Conduct Organizational Readiness Check

Answer: A

 

NEW QUESTION 71
What information does the project team need before they can correctly estimate the relative size of backlog user stories?

  • A. Definition of Done
  • B. Test strategy
  • C. Available project resources
  • D. Overall project schedule

Answer: A

 