NEW QUESTION 52
SAP Activate uses concepts, ceremonies, roles introduced by SCRUM methodology and expands them with Solution Implementation specifics.
- A. True
- B. False
Answer: A
NEW QUESTION 53
In which tools can the project team across the SAP Activate Methodology content including accelerators? There are 2 answers to this question.
- A. SAP Jam
- B. Roadmap Viewer
- C. SAP Community Network
- D. SAP Service Marketplace
Answer: A,B
NEW QUESTION 54
What does SAP Activate recommend to keep team members informed and aligned?
- A. Daily team stand-up meeting
- B. Daily e-mail status updates to project manager
- C. Daily progress review meeting with sponsor
- D. Daily status meeting with project manager
Answer: A
NEW QUESTION 55
What is a strategy level 0 (L0) artifact?
- A. Approach document that is developed by a united project team (partner + customer)
- B. Optional information that is NOT important for project activities
- C. Preliminary strategy developed by the customer to approach the project in a specific area
- D. Project result that is developed solely by the partner
Answer: C
NEW QUESTION 56
What is the most granular level of the methodology you can view in the SAP roadmap viewer?
- A. Deliverables
- B. Task
- C. Scenario
- D. Phase
Answer: B
NEW QUESTION 57
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape?
There are 2 answers to this question.
- A. P-system
- B. DEV
- C. Starter system
- D. QAS
Answer: B,D
NEW QUESTION 58
Which of the following are benefits of using ready-to-use content? Note: There are 2 correct Answers to this question.
- A. Exhaustive solution documentation
- B. Predictable results
- C. Minimized total cost of ownership
- D. Fast time-to-value
Answer: B,D
NEW QUESTION 59
In which phase do you create "an ordered list of everything that is known to be needed in the Product?
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: D
NEW QUESTION 60
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
- A. Validation Workshops
- B. Data Migration Approach
- C. Design for the Gaps and Deltas
- D. Baseline Build
- E. Solution Scope and Value Determination
Answer: A,B,C
NEW QUESTION 61
Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?
- A. Simplification and custom code impact analysis
- B. Solution validation and Delta design
- C. Fit-to-standard
- D. Setup and enablement
Answer: C
NEW QUESTION 62
What are some of the benefits that apply to SAP Cloud ALM as a cloud product? Note: There are 2 answers to this question.
- A. The solution is always available.
- B. User management is provided.
- C. The solution is always up to date.
- D. Different customer landscapes are all managed by SAP.
Answer: A,C
NEW QUESTION 63
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the answer.
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: C
NEW QUESTION 64
What are some of the capabilities end users can utilize to adapt and change their launchpad home page according to the way they work?
- A. Rearrange or move tiles within a group
- B. Delete a predelivered group
- C. Add any SAP Fiori apps to a group, regardless of role
- D. Add a new group
- E. Rename a predelivered tile
Answer: A,D,E
NEW QUESTION 65
What are the three elements of SAP Activate? There are 3 correct answers to this question.
- A. Focused Build Content
- B. Methodology
- C. Content
- D. Tools
- E. SAP Solution Manager
Answer: B,C,D
NEW QUESTION 66
What activities do you perform during the fit-to-standard workshops milestone in the SAP Activate methodology within SAP Cloud ALM? Note: There are 3 correct Answers to this question.
- A. Create notes and/or requirements in SAP Cloud ALM.
- B. Create wireframes for user interfaces in SAP Cloud ALM.
- C. View details of business process diagrams and descriptions in SAP Cloud ALM.
- D. Create SAP Fiori screen mock-ups in SAP Cloud ALM.
- E. View details of high-level process flows in SAP Cloud ALM.
Answer: A,C,E
NEW QUESTION 67
Which of the following types of monitoring are part of SAP Cloud ALM for operations? Note: There are 2 answers to this question.
- A. Event and alert monitoring
- B. Business process monitoring
- C. Business user monitoring
- D. Integration and exception monitoring
Answer: B,D
NEW QUESTION 68
Which core capability of SAP Cloud ALM for implementation supports the management of the requirements lifecycle?
- A. Task Management
- B. Process Management
- C. Change and Deployment Management
- D. Test Management
Answer: C
NEW QUESTION 69
Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 answers to this question.
- A. Reporting functional specifications
- B. Functional specifications
- C. Functional test scenarios
- D. User acceptance test-plan
Answer: C,D
NEW QUESTION 70
What do you do during post cutover?
- A. Perform the Verification Session of the SAP Going Live Check
- B. Setup Operational Support
- C. Perform Technical System Test
- D. Conduct Organizational Readiness Check
Answer: A
NEW QUESTION 71
What information does the project team need before they can correctly estimate the relative size of backlog user stories?
- A. Definition of Done
- B. Test strategy
- C. Available project resources
- D. Overall project schedule
Answer: A